Vila Nova Wind Farms in Portugal
EDP Renewables
Vila Nova I:
Vila Nova I wind farm Sub equipment with the installation of 2 wind turbines VESTAS with installed capacity of 4 MW, improvement and construction of approximately 750m accesses, trench opening and installation of cables in about 1000m.
Vila Nova II:
Power Reinforcement of Vila Nova II wind farm with the installation of 2 wind turbines ENERCON with installed capacity of 4 MW, improvement and construction of approximately 650m accesses, trench opening and installation of cables in about 900m.
Type:
Infrastructure, Renewable Energy
Country:
Portugal
Location:
Miranda do Corvo
Start date:
2013
Final date:
2013