Wind and solar farms - VOTORANTIM ENERGIA
VOTORANTIM ENERGIA
Ventos do Piauí Wind Farms - Phases II and III
Phases II and III of the Ventos dos Piauí Wind Farms are located in the municipality of Curral Novo do Piauí, PI and have 409.2 MW of installed power.
The project has 93 Vestas V150 4.4MW, HH 120 wind turbines with metal towers and a total of 10 wind farms, divided into 5 farms with 47 turbines in phase II and 5 farms with 46 turbines in phase III.
The energy generated by the wind turbines is collected by a 200km 34.5kV medium-voltage network and sent to the 34.5/230kV elevator substation in each phase, from where a 230kV transmission line runs, one of which is approximately 5km long and the other approximately 9km long, to the Curral Novo do Piauí II 230/500kV substation, where there are 2 230/500kV connection bays.
UFV Sol do Piauí
Provision of owner's engineering services for project approval, management and supervision of the implementation activities of the Sol do Piauí Photovoltaic Plant.
The project consists of 2 photovoltaic plants, in the same region as the Ventos do Piauí complex, totaling around 84.8 MWp of installed power made up of approximately 160,080 solar modules.
Sol de Jaíba Photovoltaic Park
The Sol de Jaíba Photovoltaic Park is located in the town of Jaíba, in the state of Minas Gerais, with a peak power of 629.87MWp and installed power of 500MWn. The project includes 957,066 655Mp, 660Mp and 665Mp photovoltaic modules, an 8.7km transmission line, a 230kV Connection Bay and a 34.5/230kV substation with two 230kV transformers.
Type:
Infrastructure, Energies
Country:
Brazil
Location:
Piauí - PI and Jaíba - MG
Start date:
2020
Final date:
2024