Pirapora Photovoltaic Parks

EDF / Canadian Solar


Installation of 11 solar parks in the municipality of Pirapora, State of Minas Gerais, totalizing a value of 399MWp of installed capacity.

 

Phase 1

Installation of 5 Solar Parks of 31MWac each, totalizing approximately 191MWp of installed power, 594.750 photovoltaic modules, 6.709 Trackers, 86.000 Stakes and 40 MV Stations.

It includes a collection / elevating substation located next to the parks, where each park is connected to the substation by a 34.5KV collection network. The substation has a 178MVA transformer to raise the voltage from 34.5KV to 138KV, and the complex also includes the construction of a 10.5km TL in 138kV that connects the substation of the solar parks to the connecting bay in the Pirapora 2 substation.

 

Phase 2

Installation of 6 Photovoltaic Parks totalizing 174MWac - 207.6MWp of installed capacity.

Vazante I, Vazante II and Vazante III: 92.6MWp of installed power, 285.732 photovoltaic modules, 2.830 Trackers, 41.316 Stakes and 21 MV Stations.

Pirapora II, Pirapora III and Pirapora IV: 93 MWac - 115MWp of installed capacity, 354.612 modules, 3.638 Trackers, 51.278 Stakes, 24 MV Stations.

Type:

Infrastructure, Energies

Country:

Brazil

Location:

Pirapora, MG

Start date:

2016

Final date:

2018