Ribeiradio and Ermida Hydroeletric Dams
EDP / MARTIFER
Ribeiradio Hydroelectric Dam of concrete, gravity profile, of about 78m heigh and 270m crest length.
Ribeiradio Hydro Power with non-reversible group of 72MW.
Restoration and repositioning of EM569 (Municipal Road) with 2,1km extension and bridge with 3 spans of 38m, 32m and 20m board high from the water level.
Electrical Substation in Ribeiradio Dam with Power Transformer 11/60kV, with apparent power of 1x82MVA.Over Head Line (OHL) 60kV of 22km until Mouriscas DSO Electrical Substation where all produced energy is injected to the National Grid.
Ermida Counter Dam, for modulation of the rates flow from Ribeiradio Plant, comprised by gravity Ermida Dam of conventional concrete, 35m height and 175m span, with total capacity power of 7MW.
Type:
Hydraulic works, Dams and River Works
Country:
Portugal
Location:
Sever do Vouga
Start date:
2010
Final date:
2015