Fatela / Penamacor Substation

Rede Ferroviária Nacional - Refer, E.P.E.


Castelo Branco/Covilhã leg of the Beira Baixa Line: assembly and civil works on the Fatela/Penamacor substation, including services and tests necessary for the proper operation of the facilities; work to implement measures to minimise environmental impact; additional construction works, including the installation of cables, water and sewerage networks, Electromechanical Installations, Signaling and safety. Additional landscaping works.

Type:

Infrastructure, Railways

Country:

Portugal

Location:

Fundão

Start date:

2008

Final date:

2010